When adding a new PM, the steps are as follows:
- Define the program.
- Define the activities for the program
- Once activities have been defined, you can:
- Identify sub-programs, if
applicable
- Identify the components that
are affected by the PM, if applicable
- Once components have been identified, you can:
- Identify the equipment groups
that are covered
- Once equipment groups have been identified, you can:
Change
PM rules, if required
If using sliding
PMs, add PM patterns
Once PM patterns
have been added, you can: