Process bill forecast
Note that multiple users can be in this function, processing information,
at the same time. You can, of course, select any record to bill that is
not already selected. If another user has already selected the record,
then the program will not select it for you. If you deselect records at
any level, the program will not deselect a record that has already been
selected by another user.
- At the Asset Management main menu, select Customer
| Billing | Billing Forecast. The Contract
Billing Forecast display screen appears.
- Select
the records to post, if not already selected.
- Click Post to Billing
. The Process
Bill Forecast screen appears.
- Fill in the fields as required.
- Click Enter
. The Confirm
prompt appears.
- Click Confirm.
- A new Billing Control record is created. The values are set
to indicate that this was created from the Billing Calendar rather
than the user manually submitting a job using the 'Create Billing'
menu.
- The billing control number on the forecasted billing file is
updated with the billing control number. The billing engine will
use the billing control number to determine which records to process.
Similarly, the Edit Billing Records and Print Proof will use the
billing control to determine the set of billings to process.
- The billing job is submitted using the billing control record.
- You return to the Contract
Billing Forecast display screen, where a message appears
at the top right indicating that a billing batch now exists.
- Note: The post program runs in batch mode. To view the batch
you have created, click Edit
Billing and it will show you the status of the batch
that is being created. You can continue selecting/deselecting
records at any time and create another batch if you want to. Of
course, records already on a batch will stay on that batch and
you cannot deselect records that are on a batch.
- Once the status of the batch is Create Complete, you can edit that billing batch.
Back to Billing