Start time on a work order line
- At the EMMS main menu, click the Work
Orders button. The Work
Orders display screen appears.
- Right-click on the work order and select Change.
The Edit Work Order
change screen appears.
- Right-click on the line and click Start.
If you are currently working on another work order or work order line,
one of 2 screens will appear:
- The Assign Work Order
Line change screen appears.
- You will have to distribute the total work order time to
the appropriate work order lines.
- Type in or select the Task Status and enter the Hours Worked
on each work order line.
- Click Enter
. The Confirm
prompt appears.
- Click Confirm.
The Enter Comments
change screen may appear. If so, enter any comments required.
- The Select Task Status
for Previous Job screen appears.
- Select the appropriate status for the task.
The system will start recording time worked on the work order line by
the person signed on to the system.
Note: The system will adjust the seconds so that the elapsed time is
an even multiple of 36 seconds (.01 of an hour). When starting the new
ETK event, the stop time on the previous event is adjusted so that it
is an even .01 of an hour; and subsequently, the start time on the new
event uses the same adjusted time.
What next?