Start time on a work order line

  1. At the EMMS main menu, click the Work Orders button. The Work Orders display screen appears.
  2. Right-click on the work order and select Change. The Edit Work Order change screen appears.
  3. Right-click on the line and click Start. If you are currently working on another work order or work order line, one of 2 screens will appear:

The system will start recording time worked on the work order line by the person signed on to the system.

Note: The system will adjust the seconds so that the elapsed time is an even multiple of 36 seconds (.01 of an hour). When starting the new ETK event, the stop time on the previous event is adjusted so that it is an even .01 of an hour; and subsequently, the start time on the new event uses the same adjusted time.

What next?