Create a sublet-only work order

  1. At the EMMS main menu, click the Work Orders button. The Work Order display screen appears.
  2. Click Add plus.jpg.
  3. Fill in the fields as required.
  4. Click Enter enter.jpg.
  5. The Sublet Work Order change screen expands.
  6. Right-click in the first Component field on the screen and select Prompt. The Select Multiple VMRS by Description screen appears.
  7. Right-click on the component for the work order and select Select. The Select Task screen appears for the component.
  8. Right-click on the task to be performed and select Select. You return to the Select Multiple VMRS by Description screen.
  9. Repeat steps 7-8 until all components have been selected.
  10. Click Exit exit.jpg. The Select Service Provider screen will appear for the first component/task.
  11. Right-click on the service provider the work on that line will be sublet to and select Select. The Enter Sublet Cost screen appears for the component/task.
  12. Type in the total cost of the sublet line for the specified service provider and click Enter enter.jpg. The Confirm prompt appears.
  13. Click Confirm. The Select Service Provider screen will appear for the next component/task.
  14. Repeat steps 11-13 for each component/task.
  15. You return to the Sublet Work Order change screen where a message identifying the PO number the work has been assigned to will appear.

What next?