Create the meter change work order
When creating the work order, enter the reading from the defective meter
on the work order header. The reading for the new meter will be entered
when the work order is closed.
- Create the work order.
- At the EMMS main menu, click the Work
Orders button. The Work
Orders display screen appears.
- Click Add
.
- The Work Order Type
to Create dialog may appear, depending on your
settings.
- If so, select the Regular
WO's radio button.
- Click Enter
.
- The Create Work Order
enter screen appears.
- Type in or select the Unit #.
- Click Enter
to get more fields.
- Type in the Reading from the defective meter.
- Click Enter
. The Edit
Work Order change screen appears.
- Add the task.
- Right-click in the Component field and select Prompt.
The Select Component Code
screen appears.
- Type meter in the Description Position To field.
- Click Enter
.
- Right-click on the Meter Change system and select Select.
The Select Task
screen appears.
- Right-click on the Exchange, New task and select Select.
You return to the Edit Work
Order change screen.
- Click Enter
to save the work order.
- Add the labor.
- Right-click on the work order line and select Labor.
The Labor Hours
add screen appears.
- In the Actual Hours field, type in the time the meter change
required.
- Right-click in the Employee field and select Prompt.
The Select Employee by Loc
screen appears.
- Double-click on the employee who did the work. You return to
the Labor Hours
add screen.
- Click Enter
to save the labor hours.
- Click Exit
to return to the work order.
- Add the part.
- Click the Parts
button. The Edit Work Order
Parts change screen appears.
- Right-click in the Item Number field for the meter change task
and select Prompt.
The Select Item
screen appears.
- Type meter in
the Item Description Contains field.
- Click Enter
.
- Double-click on the meter that was added to the unit. You return
to the Edit Work Order Parts
change screen.
- Make sure the Quantity is correct.
- Click Enter
to save the part.
- Click Fully Issue Parts.
The Status of the part will change to F.
- Click the Work Order
button to return to the work order detail.
- Close the work order.
- Click the Close WO
button. The Close Work Order
screen appears.
- Click the Perform Close
button. Because you used the Meter Change operation code, the
Metric Measurements
change screen appears.
- Click Meter Changes
. The WO
Meter Change change screen appears.
- In the Measurement field, type in the reading from the new
meter.
- Click Enter
to save the new meter reading.
- Click Exit
.
- If the Requisitioned Parts
Not Installed screen appears, click Exit
.
- If the Confirm Changes
screen appears, click Update
Component List.
- The Approve WO
display screen appears.
- Click Approve
.
- Click Exit
to return to the menu. The meter has been successfully
changed.
- You can now check
that the LTD value is accumulating correctly.
Back to Change a Meter