Customer incremental hours
It is possible to have the hours billed on a shop invoice be calculated
based on a quantity entered on a work order line. For example, bill 3
hours for the first 4 feet of a container repair and 1/2 hour for every
additional foot. In order to do this, incremental hours must be defined
at the customer or customer class level.
- At the Asset Management main menu, click the Customer
button. The Work with Customers
display screen appears.
- Right-click on the customer and select Std
Bill Hrs. The Customer
Standard Billing Hours - All Customer Hours display screen
appears.
- Click Incremental Hours
. The Customer
Incremental Hours display screen appears.
- If necessary, click Show All/Selected
to view all tasks.
- Right-click on the task that requires incremental hours and select
Change. The Incremental
Hours add screen appears.
- Fill in the fields as required.
- Click Enter
to save the incremental hours.
Back to Customer Master