Create a new assignment record

  1. At the Asset Management main menu, select Assets / Asset Level Depreciation | Work With Assets. The Display Assets - All Assets screen appears.
  2. Right-click on the asset and select Manage Unit Assignments. The Unit Assignment History for Asset screen appears, listing all unit assignments for the asset.
  3. Click Change Unit Assignment change.jpg. If there is already a future assignment record, you will see the error message "Change Assigned Unit not allowed. Future Assignment exists." Otherwise, the Change Asset's Unit Assignment enter screen appears.
  4. Select the new unit the asset will be assigned to (only owned units will appear on the selection screen).
  5. Enter the assignment date. If you enter a future assignment date, the Confirm Future Date Change screen will appear.
  6. Click Continue. You will return to the Change Asset's Unit Assignment enter screen.
  7. Click Change Unit Assignment change.jpg.

Back to Assets