Milestone control table
Milestones are specific points to be met during the equipment ordering
process. The milestone control files allows one or more milestones to
be set by pool to define the points to be tracked. A milestone may be
based on the date the equipment is expected, the date it is received,
the date the PDI is completed, or some other notable event. The duration
of the task resulting in the milestone may be specified. A late milestone
report is available for monitoring performance.
- At the Asset Management main menu, select Administration
| Tables | Acquisition | Milestone Control. The Display Milestones screen
appears.
- Click Change
. The Edit Milestone
change screen appears.
- Click Add
.
The Edit Milestone
add screen appears.
- Fill in the fields as required.
- Click Enter
to save the milestones.
- If a milestone will be limited to specific pools:
- Click Change
. The Edit
Milestone change screen appears.
- Right-click on the milestone and select Change
Pools. The Edit
Milestone Pool change screen appears.
- Click Add
. The Edit Milestone
Pool add screen appears.
- Select the Pools that will be affected by
the milestone.
- Click Enter
to save the pools.
- Click Exit
to return to the Edit
Milestone change screen.
Back to Acquisition Tables